Vidraru Dam Upgrade Project: Complex On-Site Logistics in a Challenging Mountain Environment
Hydropower infrastructure projects are among the most demanding undertakings in the industrial sector. They require a perfect alignment of engineering expertise, specialized equipment, and calculated execution—especially when the site is a historic engineering marvel built into a steep mountain face. For the landmark Vidraru Dam upgrade project, Eastship was employed by Electromontaj to handle the high-stakes on-site offloading, maneuvering, and precision foundation placement


Fractionator Transport – Integrated Refinery Logistics Project
Transporting a 400-ton refinery component over 210 kilometres is already a complex engineering task. Reaching its final destination proved even more demanding. As part of a larger refinery development project, Eastship Projects & Logistics managed the complete logistics scope for the transportation and final positioning of the fractionator—the largest component within a series of oversized process equipment deliveries. From transport engineering and route preparation to the d


Refinery Modules
2 sets of refinery modules each consisting in 10 modules of 2500 x 500 x 500 cms weighing up to 80 tons


Kostolac B Thermal Power Plant
700,000 Freight tons Duration: 7 years >25 millions km by truck >700 000 km by barge Kostolac B Thermal Power Plant is an ongoing 697 MW coal-fired power project located in Branicevo, Serbia. The project has been developed in multiple phases and is expected to achieve stable operation on the grid in September 2023. Since 2016, Eastship has been a key logistics partner in the power plant’s construction, delivering around 700,000 freight to the site in Serbia, over 25 million k


5972 Oil Rig Relocation
The 2020 oil rig relocation project undertaken by Eastship presented unique challenges that required precise planning and execution. One of the primary challenges was the short execution time of only 10 days, which left no room for delays that could have resulted in significant losses for our client. At Eastship, we pride ourselves on our commitment to meeting such challenges, and we assembled a team of professionals who were ready to work tirelessly to ensure the project’s t


STB Bus transport
Eastship successfully transported a batch of 30 electric buses for the public transportation system in Bucharest. These buses, which form part of a larger order of 200 units, were efficiently delivered to their destination, showcasing our expertise in handling specialized and large-scale cargo. The electric buses, measuring 12 x 2.5 x 3.3 meters, boast a fully electric traction system and a minimum range of 200 km between charges. With features like a lowered floor, three dou


Factory relocation Project
The project encompassed the transport of various cargo, including gantry cranes, girders, steam boilers, flying buckets, panels, and air compressors, efficiently packed in ninety 40’ OT/Flat Racks. Notably, oversize cargo pieces measuring 28-32 meters, like gantry cranes and girders, were also part of the consignment. Our team met with the Port authorities to take special approval from concerned authorities for priority berthing. To ensure the special transport was handled sa


640 km - Crane Delivey
As part of the modernization of the UMM Râbnița, Eastship transported a rough terrain crane from the renowned Japanese company TADANO. After a long journey of over 640 km the machinery was safely delivered to the Rabnita site. This notable machinery marks a significant milestone not only for the plant but also for the entire region. With a remarkable 93-metre arm span and 145 tons lifting capacity, this crane boasts capabilities that enable intricate repair work at substantia


Porto nogaro
We were contracted to pick up four heavy reactors from a port in Italy, a location that presented significant logistical challenges due to the absence of any suitable heavy lifter capable of reaching the site. This particular port, known for its limited access points and difficult terrain, required a carefully crafted approach to ensure the safe and efficient handling of heavy equipment transport. In less than one day, our dedicated logistics team conducted a thorough analysi


HVT transport to Nuclear Power Plant
In 2022, Eastship Projects & Logistics successfully completed the transportation of two high voltage transformers for the Cernavodă Nuclear Power Plant, one of Romania's critical energy infrastructure facilities. The project involved the movement of heavy electrical equipment under a highly restrictive delivery schedule, requiring careful coordination, detailed engineering, and the integration of multiple transport modes. With a delivery window of only three days, conventiona


L.N.G. Tanks
This was one of the most challenging transportation projects Eastship`s team has ever faced. We were entrusted with the transportation of two massive tanks to the VARD shipyard in Tulcea. The tanks weighed a staggering 366 tons each and measured 28 metres in length, 15 metres in width, and 12 metres in height. The first challenge was to find a barge that could transport the tanks from Constanta and transport them to Tulcea. However, the Tulcea dock posed a unique challenge. T


Rompetrol Cogeneration Plant
The construction of the cogeneration plant is the most significant project of the Kazakh-Romanian Energy Investment Fund (FIEKR), and it is a crucial pillar for both the Petromidia refinery and the national energy system. The complex industrial project was built in about 3 years. Eastship was a logistic partner for this project, handling all details of the deliveries: unloading on modular trailers or specialised semi trailers, temporary storage on elephant legs, engineering,


Iernut Power Plant
As part of the Iernut project in 2024, Eastship transported seven autoclaves over a distance exceeding 700 kilometers. Each autoclave measured 24 meters in length, 3.3 meters in height, 3 meters in width, weighed 45 tons. For the internal movement at beneficiary’s premises, we have used a tailor made system engineered, built and operated by our crew. We designed and constructed robust trolleys, each capable of supporting 45 tons, and mounted them on rails. The autoclaves we


Transport of the Largest Pressurized Vessel Ever Built in Romania
Industrial infrastructure developments demand highly specialized engineering and rigorous route planning, particularly when transporting record-breaking components across international corridors. Eastship Projects & Logistics managed the complete end-to-end transport of the largest pressurized vessel ever built in Romania. This high-tonnage component was delivered as a critical asset for the Midor Oil Refinery Expansion Project located in Egypt. Project Specifications & Heavy


Barge Transport & Transshipment of Industrial Boilers
When seasonal low-water levels on the Danube River threatened a critical heavy-lift timeline, Eastship's engineering team deployed specialized shallow-draft solutions to safely transport three 364-ton industrial units. Discover how precise draft calculations, short-notice fleet mobilization, and a direct vessel-to-vessel transhipment of big boilers at the Port of Constanta kept this 1,092-ton global supply chain project moving smoothly toward Doha, Qatar.


Centimeters to Spare: A Complex Reactor Barge Operation
In the world of project logistics and oversize transport, no two voyages are identical. Every cargo presents unique structural dimensions, and every waterway introduces its own variables. Out of the numerous barge operations executed each year, one recent project highlighted exactly how critical technical precision becomes when physical space is at an absolute premium. The objective: transport two industrial reactors of massive magnitude. While moving cargo of this scale alwa


Vidraru Dam Upgrade Project: Complex On-Site Logistics in a Challenging Mountain Environment
Hydropower infrastructure projects are among the most demanding undertakings in the industrial sector. They require a perfect alignment of engineering expertise, specialized equipment, and calculated execution—especially when the site is a historic engineering marvel built into a steep mountain face. For the landmark Vidraru Dam upgrade project, Eastship was employed by Electromontaj to handle the high-stakes on-site offloading, maneuvering, and precision foundation placement


How Eastship Delivered the "Moles" Modernizing Romania's Railways
Discover how our project logistics team executed the complex, 500 km oversize transport of massive Tunnel Boring Machines (TBMs) from Constanța Port through the narrow mountain passes of the Prahova Valley (DN1). Learn how meticulous route planning and specialized heavy-lift engineering safely delivered the critical equipment shaping the future of the Sighișoara-Brașov high-speed railway line.